Math, asked by rishika8a, 10 months ago

A and B can do a piece of work in
18 days, B and C in 12 days and C and Ain
18 days. Find the time in which A, B and
C working together can finish the work​

Answers

Answered by biligiri
1

Answer:

A and B one day work = 1/18.......1

B and C one day work = 1/12.......2

C And A one day work = 1/18.......3

add 1, 2 and 3

A+ B + B + C + C + A = 1/18+1/12+1/18

2 ( A + B + C ) = (2 + 3 + 2)/36

2 ( A + B + C ) = 7/36

A + B + C = 7/36*1/2

=> 7/72

means A , B and C together can complete 7/72th

of work in a day.

by taking the reciprocal, we can get number of days they will complete the job working together

72/7 =10 ²/₇ days