Math, asked by khansouravkumar, 11 months ago

A and B can do a piece of work in 40 days, B
and C in 30 days, and C and A in 24 days.-
(i) How long will it take them to do the work,
working together?
(ii) In what time can each finish it working alone ?​

Answers

Answered by toratnesh
0
1)15days is our correct answer
Answered by jivya678
0

Total time taken by A, B & C working together = 11.42 days

Time taken by A to complete the work = 18.46 days

Time taken by B to complete the work = 21.83 days

Time taken by C to complete the work = 16 days

Step-by-step explanation:

(1). Work done by A & B in one day =  \frac{1}{40}

Work done by B & C in one day =  \frac{1}{30}

Work done by C & A in one day =  \frac{1}{24}

Work done by A, B, C working together =

2 ( A + B +C ) = \frac{1}{40} + \frac{1}{30} + \frac{1}{24}

⇒ 2 ( A + B +C ) = \frac{21}{120}

⇒ A + B +C = \frac{21}{240}

⇒ A + B +C = \frac{7}{80}

This is the work done by A, B & C working together.

Now total time taken by A, B & C working together = \frac{80}{7} = 11.42 days

(2). Work done by C in one day = \frac{7}{80} - \frac{1}{40}

W_{C} = \frac{1}{16}

⇒ Thus time taken by C to complete the work = 16 days

Work done by A in one day = \frac{7}{80} - \frac{1}{30}

W_{A} = \frac{13}{240}

Time taken by A to complete the work = \frac{240}{13}

⇒ Thus time taken by A to complete the work = 18.46 days

Work done by B in one day = \frac{7}{80} - \frac{1}{24}

W_{B} = 0.0458

Time taken by B to complete the work = \frac{1}{0.0458}

⇒ Thus time taken by B to complete the work = 21.83 days

Similar questions