A and B can do a work in 12 days, B and C can do the same work in 15 days and A and C
can complete the work in 20 days. In how many days A, B and C working together can
complete the whole work?

with steps please
i will mark as the brainliest if with steps​

Answers

Answered by awcharranjana875
2

Answer:

10 days

Explanation:

Number of days taken by A & B to complete work = 12 days

Number of days taken by B & C To complete same work = 15 days

Number of days taken by A & C to complete Same work = 20 days

L. C. M of 12, 15 & 20 = 60

Number of unit done by A & B

=60/ 12 = 5

Number of unit done by B & C

=60/15 = 4

Number of unit done by A & C

=60/ 20 = 3

Number of days taken by A , B and C together

[Next step I had write on paper I had sent you can see]

Attachments:
Answered by spencer11
0

Answer:

Pls mark me as brainliest

Explanation:

A+B(1day's) = 1/12 work

B+C(1day's) = 1/15 work

A+C(1day's) = 1/20 work

Adding all the above

2 (A+B+C) (1day's) = 1/12 + 1/15 + 1/20

2 (A+B+C) (1day's) = (5+4+3)/60

2 (A+B+C) (1day's) = 12/60

2 (A+B+C) (1day's) = 1/5

:. (A+B+C) (1day's) = 1/10

Hence, A,B and C can complete the whole work in 10 days.

Pls mark me as brainliest