a and b can do piece of work in 16 and A alone can do in 24 days and how many days does B can do the work
Answers
Answered by
2
HIII... .
GOOD MORNING:)
HERE COMES YOUR ANSWER:--------
DAYS TAKEN BY A AND B TOGETHER TO COMPLETE THEIR WORK = 16 DAYS
DAYS TAKEN BY A TO COMPLETE THE WORK = 24 DAYS
A/Q,
1/A+1/B= 1/16
1/24+ 1/B= 1/ 16
SO,
1/B= 1/16+1/24=1/48.
HOPE THIS HELPS YOU......
Answered by
0
Given,
And,
-» a = 24.........(1)
Now, SUBSTITUTING in given equation, we get,
-»
-»
-»
Therefore, B takes 48 days to complete the work.