A and B can do work in 60 days, B and C can do the same work in 40 days. If time taken by A alone is 4 days more than the time taken by C alone, then in how many days work will be completed by A and C together? (Consider B is doing negative work)
Answers
Answer:
Step-by-step explanation:120/11
A and C together will complete the work in 72 days.
We can use the formula:
where A and B are the number of days taken by two workers to complete a task, X is the number of days taken by both workers to complete the same task.
We know that A and B can do the work in 60 days and B and C can do the same work in 40 days. So, we can use this information to find the time taken by A and C together to complete the work.
We know that time taken by A alone is 4 days more than the time taken by C alone.
Let's assume the time taken by C alone is x, then the time taken by A alone will be (x + 4) days.
We can use this information to find the value of X:
Solving the equation, we get X = 72 days.
So, A and C together will complete the work in 72 days.
To know more about work visit
https://brainly.in/question/12207321
https://brainly.in/question/29618011
#SPJ2