A and B complete a work in 6 days and A alone can do the same work in 10 days
then B alone will do​

Answers

Answered by jyotimehta6667
1

answer = b will alone do in 16days

Step-by-step explanation:

a and b=6

for a =3days

for b =3days

a can do in 10 days

b=x

x - 6=10

x=10add 6

x=16

Answered by muskanyadav12
1

Answer:

B can complete the work in 15 days

Step-by-step explanation:

A and B can complete a work in6days

A and B one day work =1/6

A can alone do the work in 10 days

A's one day work=1/10

B's one day work = 1/6 -1/10

= 2/30

=1/15

B can alone do the work in 15 days