A and B together can complete a piece of work in 15 days. They started
working together but after 11 days, A left. The rest of the work is completed
by B in 12 days. In how many days can A alone do the whole work?
Answers
Step-by-step explanation:
a and b can complete the work in 15 days.
Percentage of work done by a and b in one day = 100/15=6.66%
b alone can complete the whole work in 20 days.
So, percentage of work done by b in one day = 100/20=5%
Percentage of work done by a in one day = 6.66-5=1.66%
Thus, a can complete the whole work alone in = 100/1.66=60 days (approx)
Alternatively,
a and b can complete the work in = 15 days
Part of work done by a and b in one day= 1/15
b can complete the work alone in = 20 days.
so, part of work done by b in one day = 1/20
Part of work done by a = 1/15 - 1/20= 1/60
a can complete the work in = 1/(1/60) = 60 days.
C
Answer:
A and B complete work together in 15 days
Step-by-step explanation:
B alone completed in 12 days , so that's why
= 15×12÷15-12
=180÷3
=60
A alone do the whole work in 60 days
I think this is the most simple way to solve this question and you find this helpful