A and B together can do piece of work in 16 days and A alone can do it in 48 days. How many long will B take to complete the work?
Answers
Answered by
30
Answer:
Given :
- A and B can do a piece of work in =16 days
- A alone can do the same piece of in = 48 days
What to find out = how many days will B take to complete this work?
Solution :-
(A+B)'s 1 day work= 1/16
A' s 1 day work = 1/48
Hence B's 1 day work= (1/16)-(1/48)
=(3-1)/48=1/12
So ,B alone can complete the work in 12 days.
Answered by
16
Answer:
24 days
Step-by-step explanation:
(A+B)'s 1 day's work =1/16
A's 1 day's work =1/48
B's1 day's work=1/16-1/48
=3-1/48=2/48=1/24
B alone can complete the work in 24 days