A and B working together can complete a work in 'D' days . Working alone A takes (8+d) days and B takes (18+d) days to complete the same work. A works for 4 days , so the remaining work will be completed by B alone in how many days ?
Answers
The remaining work will be completed by B alone in 24 days .
Step-by-step explanation:
Given as :
A and B working together can complete a work in 'd' days
A alone can work in 8 + d days
So, A's 1 day work =
B alone can work in 18 + d days
So, B's 1 day work =
And
(A + B)'s 1 day work =
Again
(A + B)'s 1 day work = A's 1 day work + B's 1 day work
i.e = +
Or, = 18 + d + 8 + d
Or, 144 + 8 d + 18 d + d² = d ( 26 + 2 d)
Or, 144 + 26 d + d² = 26 d + 2 d²
Or, 2 d² - d² = 144
Or, d² = 144
∴ d = √144
i.e d = 12 .............1
So, A and B together can complete work in d = 12 days
Again
A works for 4 days , so the remaining work will be completed by B alone
So, ∵ A's 1 day work =
∴ A's 4 day work = × 4 =
Rest of the work is done by B alone
rest of work = 1 -
=
=
Now,
∵ work is done by B in 1 day
∴ work is done by B in × day
= days
Put the value of d = 12 from eq 1
= days
= days
= 24 days
So, The remaining work will be completed by B alone in = 24 days
Hence, The remaining work will be completed by B alone in 24 days . Answer
Step-by-step explanation:
(8+12)
(4+12)(18+12)
days
= \dfrac{16\times 30}{20}
20
16×30
days
= 24 days
So, The remaining work will be completed by B alone in = 24 days
Hence, The remaining work will be completed by B alone in 24 days . Answer