A and B working together can finish a piece of work in 6 days while a alone can do it in 9 days how much time will be alone take to finish it
Answers
Answered by
20
Answer:
18 days
Step-by-step explanation:
A and B can together do 1 work in 6 days
So, work done in 1 day by both of them together= 1/6
A can do 1 work in 9 days
So, work done in 1 day by A= 1/9
NOW,
Work done by A in one day +Work done by B in one day
= Work done by A and B together in one day
1/9 +Work done by B in one day = 1/6
Work done by B in one day= 1/9-1/6
=3-2/18
= 1/18
So, B can do 1 work in 18 days.
himanshu5395:
Thanks............ so.............much