Math, asked by Sony75181, 9 months ago

A B and C can do a piece of work in 8 days 12 and 15 days respectively how long will it take to finish it if they work together

Answers

Answered by AshnaChadha
1

Step-by-step explanation:

A's one day work=1/8

B's one day work =1/12

C's one day work=1/15

Together=1/8+1/12+1/15

add and find the ans