A, B, C do a work in 10, 15 and 7 days respectively. A and B start the work and A leaves after 5 days. Then C join B in how many days will the remaining work now be completed?
Answers
Answered by
1
Hey Dear,
◆ Answer -
35/44 day
◆ Explanation -
Given that A, B and C do a work in 10, 15 and 7 days respectively. So A, B and C can do 1/10th, 1/15th and 1/7th work in one day.
In 5 days, part of work completed is -
Work completed = 5 × 1/10 + 5 × 1/15
Work completed = 5/6 th work
Remaining 1/6th work is completed by B and C in x days.
Remaining work = x × 1/15 + x × 1/7
1 - 5/6 = x × 22/105
x = 1/6 × 105/22
x = 35/44 day
Therefore, 35/44 day are required to complete remaining work.