A can complete a certain job in 12 days. B is 60% more efficient than A. In how many days can B complete the same job?
Answers
Answered by
0
b will complete the work in 4.8days
Attachments:
![](https://hi-static.z-dn.net/files/df8/acdf111651a0485897679a3550ae5537.jpg)
Answered by
4
B is 60% more efficient than A, means that the rate of B is 1.6 times as greater as that of A
So if A can complete the job in 12 days, then B complete the same job in 12/1.6 = 12/(8/5) = 15/2 = 7.5 days.
So if A can complete the job in 12 days, then B complete the same job in 12/1.6 = 12/(8/5) = 15/2 = 7.5 days.
RohitKumar20:
will u plzz help me to solve the problems of phy n chem
Similar questions