A can do a job in 12 days. B is 60% more efficient than A. How many days does B alone take to do the same job ?
Answers
Answered by
1
60% of 12 =7.2
So, B will do the work in (12-7.2)= 4.8days.
So, B will do the work in (12-7.2)= 4.8days.
Similar questions