Math, asked by Anant4429, 1 year ago

A can do a piece of work in 12days,b can do it in 16 days.A started to work alone . After how many days should b join him,so that the work is finished in 9 days?

Answers

Answered by amitnrw
0

Answer:

After 5 Days

Please mark the answer as "The Brainliest answer" if it helps

Step-by-step explanation:

A's 1 day work = 1/12

B's 1 day work = 1/16

Let A do alone work for x days

remaining days = 9-x

x/12 + (9-x)(1/12 + 1/16) = 1

x/12 + (9-x) (4 + 3)/48 = 1

4x + (9-x) (7) = 48

4x + 63 - 7x = 48

- 3x = - 15

x = 5

After 5 days B should join A