A can do a piece of work in 15 days. B can do the same work in 12 days and C can

finish the same piece of work in 20 days. They started the work together for 2 days

and then B and C leaves. In how many days will A finish the remaining work​

Answers

Answered by ms4809856
0

in 5 day they were completed the work