Math, asked by vakhariajenifer, 11 months ago

A can do a piece of work in 20 days while B can do it in 15 days. With the help of C they finish the work in 1 days. In what time would C alone do it?​

Answers

Answered by Anonymous
1

Total work = LCM of 20 and 15 = 60

One day work of A = 60/20 = 3

One day work of B = 60/15 = 4

If one day work of C = x, then

According to the question :

 \frac{60}{3 + 4 + x}  = 1 \\  \\  =  > 3 + 4 + x = 60 \\  \\  =  > x  = 53

One day work of C = 53

C will complete the total work in = 60/53 days

Your question is absolutely wrong so check it once again but according to your question answer is 60/53 days.

I hope it will be helpful for you ✌️✌️