A can do a piece of work in 25 days and b can do the same work in 30 days. They work together for 5 days, how much of work is left ?
Answers
Answered by
9
Answer:
A can complete work in 1 day = 1/25
B can complete work in 1 day = 1/30
A and B together complete work in 1 day =
1/25 +1/30= 6+ 5/150
=> 11/ 150
There 5 days work together = 5 × 1 day work
=> 1- 55 /150
=> 95 / 150
Now remaining work is done by B
Let B takes X days to complete it
then,
1/30× X = 95/150
=> 95×30 /150
=> 19 days Remaining
=============
@GauravSaxena01
Similar questions