A can do a piece of work in 8 days and B can do it in 6 days. How long will they take to complete it together
Answers
Answered by
2
Answer:
Step-by-step explantion:
Total work = 24 ( lcm of 8 and 6)
Efficiency of A = 24/8
= 3
Efficiency of B = 24/6
= 4
Together they complete in,
24/7 (Total work/Total efficiency)
=3.43 days
Answered by
2
Answer:
3 days
Step-by-step explanation:
A complete work in 8 days
so, A complete work in 1 day = 1 / 8
B complete work in 6 days
so, B complete work in 1 day = 1 / 6
thus, together both work = 1 / 8 + 1 /6
so , the
LCM of 8 and 6 = 24
3 + 4 / 24
7 / 24 days
so, A and B take to both complete work = 7 / 24 days