Math, asked by kruti6181, 1 year ago

A can do a work in 15 days and b in 10 days ,b left after 4 days than how many days a alone can complete the work

Answers

Answered by ramsir47
0
by using lcm of 15 and 10

total work is lcm

lcm = 30

they separate per days work in united

A = 30/15 = 2 unit

B = 30/10 = 3 unit

A + B together 4 days

2 + 3 = 5 × 4 = 20 unit complete

remains work = 30 - 20 = 10 unit

A do 10/2 = 5 days