Math, asked by Shainoor, 8 months ago

A can do a work in 6 days and B can do it in 8 days. they worked togather for 2 days and then B left the work. how many days will A require to finish the work?​

Answers

Answered by yogitamishra30
2

Answer:

where is your answer it might help you if it help you please mark my answer as a brainlist answer

Attachments:
Answered by shaziakazmi3103
3

Answer:

A can do work in 1 day = 1/6

B can do work in 1 day = 1/8

A and B cand do work in 1 day = 1/6+1/8

= 4/24+3/24

= 7/24

A and B can do work in 2 days = 7/24*2 = 7/12

Remaining work = 1-7/12 = 5/12

Time taken to do remaining work = 5/12*6 = 5/2