A can finish a job in 20 days and b can complete it in 30 days. They work together and finish the job. If rs 600 is paid as wage, then the share of a and b

Answers

Answered by Anonymous
2
hope you got if any doubt ask me
Attachments:
Answered by kanchanadevi26
3

Answer:

A=360

B=240

Step-by-step explanation:

A can finish a job in 20 days

B can finish a job in 30 days

L.C.M(20,30) = 60

Efficiency of A = 60/20 = 3

Efficiency of B = 60/30 = 2

Hence, A+B=5,

600/5 = 120 Rs.

3*120 = 360 Rs.

2*120 = 240 Rs.

Hence A receives 360 and B receives 240