A can finish a work in 18 days b can do the same work in half the time taken by age and working together what part of the same work and they finish in a day
Answers
Answered by
1
a finish work in 18 days
b finish work in in 9 days
So In one day a can do 1/18 part of work
And b can be 1/9 part of work
so total part of work done by both together
b finish work in in 9 days
So In one day a can do 1/18 part of work
And b can be 1/9 part of work
so total part of work done by both together