Math, asked by sruthisajesh115, 1 year ago

A certain number of men can do a work in 60 days if thete wete

Answers

Answered by Anonymous
2
\mathfrak{The\:Answer\:is}


40 days

If there are x workers in first case 1 man will take 60x. In second it will be 50(x+8) 

60x = 50x + 400 
x = 40


\boxed{Hope\:This\:Helps}