A certain number of workers can finish a job in 30 days if after 5 days 4 more workers join in to the job to finish the job in 15 days ... find the number of workers taken to finish the job
Answers
Answered by
4
Answer:
number works need to finish the job is = 6 workers
Step-by-step explanation: