Math, asked by priyanshgond7522, 5 months ago

a contract is to be completed in 24 days and 40 men's were set to work.after 16days only half of the work was completed.how many additional men should be employed,so that the work may be completed in atime​

Answers

Answered by kakarlaakhilkumaryad
0

They will need 80 persons to complete the work in 16 days