a contractor employed 210 men to build a house in 60 days after 12 days he joined by 70 more mens in how many days will the remaining work be finished ?
Answers
Answered by
3
Answer:
210 men_60 days
1 man_60×210
(210+70)_60×210/280
" _45 days
280 men will complete this work in 45 days.