A contractor undertakes to dig a canal 12 km long in 30 days with 80 men. After 10 days he found that only 3 km of canal is completed. How many men must now be employed to finish the work on time?
GIVE ONLY RELEVANT ANSWERS WITH FULL EXPLANATION...
IRRELEVANT ANSWERS WILL BE REPORTED
CORRECT ANSWER WILL BE MARKED BRAINLIEST.
Answers
Answer:
Total time given =35 days.
To dig a canal of 2 km in 20 days, 90 men were required.
So, to dig a canal of 1 km in 1 day,
2
90×20
men will be required.
So, to dig a canal of 4 km in 15 days
15
900×4
=240 men will be required.
As 90 men were already employed, so 150 more men are required.
l hope it's help you ♥️
A contractor undertakes to dig a canal 12 km long in 30 days with 80 men. After 10 days he found that only 3 km of canal is completed. How many men must now be employed to finish the work on time?
Total time given =35 days.
To dig a canal of 2 km in 20 days, 90 men were required.
So, to dig a canal of 1 km in 1 day,
2
90×20
men will be required.
So, to dig a canal of 4 km in 15 days
15
900×4
=240 men will be required.
As 90 men were already employed, so 150 more men are required.