A contractor undertook a job and employed 40 men to do a piece of work in 80 days. But after 60 days he found that only 3/5 of the work is completed. To complete the work in time, how many more men he should employ ?
Answers
40 can do a piece of work in 80 days
they worked for 60 dAys = 3/5*60
1/36
remaining work
1 - 1/36
35/36
now'
35/36*80
solve this equation
40 additional men are required.
Step-by-step explanation:
Consider the provided information.
Use the formula:
Where M represents the number of employees, D represents the number of days, H represents the hours and W represents the part of work done.
It is given that 3/5 th of work is completed in 60 days, Now contractor need to complete the th of work in 80-60=20 days.
Let x is the total number of employees required.
Substitute the respective values in the above formula.
Total number of men required is 80 but they already has 40.
So the additional men required are: 80-50=40.
Hence, 40 additional men are required.
#Learn more
A contractor undertook to do a certain work in 75 days and employed 60 men to do it. after 25 days he found that only one-fourth of the work was done. how many more men must be employed in order that the work may be finished in time?
brainly.in/question/4046974