A is more efficient than B and they together can complete a work in 24 days.Had A done 50% of the work and then B the remalning work then the work would have been done in 50 days.B alone will complete 40% of the same work in
Answers
Answered by
0
Answer:
23 days which means 24-1=23 days
Answered by
0
b alone will complete in 24