A machine part can be manufactured in 16 days by 300 workers .If only 25%of the job is to be done in 15 days ,then how many workers need to be appointed?
Answers
Answered by
0
Please see the attachment
Attachments:
Answered by
0
800 workers need to be appointed.
Step-by-step explanation:
Since we have given that
Number of workers = 300
Number of days = 16
If 25% of work is to be done in 15 days, number of workers needs to be appointed be 'x'.
According to question,
Hence, 800 workers need to be appointed.