Math, asked by chetanm9330, 1 year ago

A machine part can be manufactured in 16 days by 300 workers .If only 25%of the job is to be done in 15 days ,then how many workers need to be appointed?

Answers

Answered by sprao534
0
Please see the attachment
Attachments:
Answered by windyyork
0

800 workers need to be appointed.

Step-by-step explanation:

Since we have given that

Number of workers = 300

Number of days = 16

If 25% of work is to be done in 15 days, number of workers needs to be appointed be 'x'.

According to question,

300\times 16=\dfrac{x\times 15}{\dfrac{1}{4}}\\\\300\times 16=x\times 15\times 4\\\\x=800

Hence, 800 workers need to be appointed.

# learn more:

If 25 workers can finish a job in 40 days, how many workers will complete the same job in 25 days?

https://brainly.in/question/6228571

Similar questions