A pile of length l carrying a uniformly distributed load wper metre length is suspended at the centre and from other two points 0.15 l from either end ; the maximum hogging moment will be
Answers
Answered by
0
Answer is option D. WL2/90
Attachments:
Answered by
0
Answer:
WL²/90
Explanation:
Pile suspended at three points: Very long piles are suspended from three points. These toggles are provided in the length of the pile. Two toggle holes are kept at a distance of 0.15 L from each end and the third toggle hole is kept in the middle of these two holes. The maximum bending moment is given by:
WL²/90