A project manager hired 15 men to complete a project in 40 days. However, after 30 days, he realized that only 1/2 of the work is completed. How many more men does he need to hire to complete the project on time?
Answers
Answered by
5
Answer:
30
Step-by-step explanation:
15 men take 30 days to complete x/2 work
(assuming x to be the total work)
so to complete the same amount of work(x/2) in 1/3rd amount of time, we need 3 times the original men=45 men
So extra men needed=45-15=30 men