a promoter employed 180 labourers to build a house in 46 days. After 5 days, 16 labours felt ill and left the job. How long will it take to complete the whole work?

Please answer fast, I will mark you as the brainliest. And please don't spam. It is urgent. ​I will follow the one who gives the correct answer faster. Please be quick.

Answers

Answered by prasanthikuchipudi
4

Answer:

50 days

Step-by-step explanation:

Given,

a promoter employed 180 labourers to build a house in 46 days.

we know,

work=men*hours*days

work is same

180 men*46 days=total

After 5 days, 16 labours felt ill and left the job.

180 men worked for 5 days

180 men* 5 days

16 labours felt ill and left the job.

if 16 members left remaining are (180-16)=164 men

164 members can do the remaining job in x days

164 men*x days

Total=180 men* 5 days+164 men* x days

180 men*46 days=180 men* 5 days+164 men* x days

x =45 days for remaining work

whole work is previously 5 days +45 days=50 days