A takes 6 days and b takes 4 days. How much will they take together
Answers
Answered by
0
A takes 6days
b takes 4days
together they take 6+4 equal to 10
so answer is 10
Answered by
1
Step-by-step explanation:
A'S 1DAY WORK=1/6
B'S 1 DAY WORK=1/4
TOGETHER 1 DAY WORK=1/6+1/4
=3+2/12
=5/12
TOGETHER CAN COMPLETE IN 12/5=2 2 1/2 DAYS