Math, asked by vipinmamgai68, 10 months ago

a work is to be finished in 12 days by 20 workers. after 8 days it is found that only 1/2 part of the work has been done. how many more workers should now be engaged in order to finish the job in time.

Answers

Answered by Edwinabraham
15
consider x no of more workers to engage to finish work on time
Attachments:

Edwinabraham: remaining days
vipinmamgai68: how you solve the 20*8/1/2 × 20 + x × 4 / 1/2
Edwinabraham: that is not i solved
Edwinabraham: just cancel all the terms lhs and rhs
Edwinabraham: just cancel the left and right side of the equation
Edwinabraham: yuo will get 20+x =20×2
vipinmamgai68: 20+ x = 20× 2 how you solve
Edwinabraham: 20+x =40
Edwinabraham: x=40-20=20
vipinmamgai68: sanju can do a piece of work in 4days and sumit can do it in 4days. how long will they take if both work together
Answered by ravikhokarmeena
13

Answer:

Answer is- 20 wrokers more need

Step-by-step explanation:

20 workers need 8 day to complete 1/2 wrok

in 1 day the need 160 wrokers

in 4 day = 160/4

in 4 days = 40 wrokers

20 worker we have then

40-20 = 20wrokers answer