Aand b together can do a piece of work in 24 days ; b and c together can do it in 20 days and c and a together can do it in 30 days . They all work together for 12 days , where a and b leave . How many days more will take to finish the work ?
Answers
Answered by
0
Answer:
Step-by-step explanation:
Let a,b and c work done by in one day and 120w is full work then
24(a+b)=120w
a+b=5w----(1)
20(b+c)=120w
b+c=6w----(2)
30(c+a)=120w
c+a=4w----(3)
addind(1),(2) and (3) we get
2(a+b+c)=15w
a+b+c=15w/2
work done by a,b and c in 12 days=12(a+b+c+)=6*15w=90w
remaining work =120w-90w=30w
now (2)+(3)-(1) we get
b+c+c+a-a-b=10w-5w
2c=5w or c=5w/2
So No of days taken by c to complete the remaing 30w work
=30w/(5w/2)=30w/1*2/5w==12 days