Activity
Immediate Predecessor(s)
Estimated Duration (days)
A
10
B
15
C
A.
2.
B
12
E
C,D
14
F
B
8
G
D, F
15
E
10
I
E, G
6
-
F, I
9
Answers
Answered by
0
Explanation:
Develop a network diagram for the project specified below:
Activity
Immediate
Predecessor
Activity
A -
B A
C, D B
E C
F D
G E, F
Solution
Activity A has no predecessor activity. i.e., It is the first activity. Let
us suppose that activity A takes the project from event 1 to event 2. Then
we have the following representation for A:
For activity B, the predecessor activity is A. Let us suppose that B
joins nodes 2 and 3. Thus we get
1 2 3
Activities C and D have B as the predecessor activity. Therefore we
obtain the following: