Compute the machine hour rate from the following data:
Total machine cost to be depreciated Rs. 2,30,000
Depreciation on straight line
Departmental overheads (annual)
Power cost Re. 0.50 per hour of running timc.
Labour (a) when setting and adjusting, full time attention
Annual cost of reserve equipment for the machines
(b) When machine is producing, one man can look after three machines.
There are 26 machines in the department.
ddle 63
1.
Life: 10 years
iv.
Rent
Heat & Light
Supervision
Departmental area
Machine area
V.
Rs. 50,000
Rs. 20,000
Rs. 1, 30,000
70,000 square feet
2,500 squarc fcct
vi.
vii.
viii.
Hours run on production
Hours for setting and adjusting
ix.
Rs. 1,500
Rs. 1,800
200
%.
Labour rate Rs. 6 per hour.
Answer
Machine hr rate Rs. 20.14]
Kan
Answers
Answered by
3
Answer:
bc itna hard questionn.
Answered by
5
Answer:
Follow the picture. It's provided in detailed version.