Example 24
20 days before B goe
s away. In how many days will A manage to finish the remaining work?
A can do a piece of work in 80 days and B in 100 days. They work together for first
Answers
Answered by
1
Answer:
Let A and B work for 20- days and then A- alone completes the work in N- days, then
(20+N)/80 + 20/100 = 1
So 5(20+N)+ 4(20) = 400
So 5N= (400- 180)= 220
So N= 220/5= 44- days
. Therefore A will finish the remaining unfinished work in 44- days.
========================== Another Simple Method:
Part of the work completed in 20- days
= 20/80+ 20/100= 1/4+ 1/5
= 9/20- part of the work.
Therefore the remaining 11/20- part of the work will be completed by A in = (11/20)÷ (1/80)= 11/20 x 80= 44- days. Ok.
=============================
Similar questions