Math, asked by ramanaga270gmailcom, 11 months ago

find the cost of digging a cuboidal pit 8 metre long 6 metre board and 3 metre deep @ rupees 30 per metre cube ​

Answers

Answered by dharampratapvirdi
5

Answer:

Step-by-step explanation:

Attachments:
Answered by harendrakumar4417
2

The cost of digging cuboidal pit is Rs. 4320.

Step-by-step explanation:

Let the length of the cuboidal pit = L = 8m

Breadth of the cuboidal pit = B = 6m

Depth of the cuboidal pit = H = 3m

Volume = L x B x H = 8 x 6 x 3 m³ = 144 m³

Cost of digging per m³ = Rs. 30

Cost of digging 144 m³ = Rs. 30 x 144 = Rs. 4320

Hence, the cost of digging cuboidal pit is Rs. 4320.