for a construction of a 12km road project there are 100 number of workers. the project should be completed in 15 days 100 worker started the work and after 9 days only 5 km of the project was completed. find the number of extra worker required to complete the project on time?
Answers
Answered by
1
Answer:
110 extra workers
Step-by-step explanation:
steps given in the image above
Hope it helps!!
Please mark as brainliest!! :)