for finishing a job A need 2 days,B need 3 days and C need 6 days. how many days needed for the same job if they work together
Answers
Answered by
0
Answer: 1 day
Step-by-step explanation: Assume the total work to be 1 .
A needs 2 days to complete the work by himself .
∴ A can do 1/2 of the work in 1 day .
B needs 3 days to complete the work by himself .
∴ B can do 1/3 of the work in 1 day .
C needs 6 days to complete the work by himself .
∴ C can do 1/6 of the work in 1 day .
∴ Together A,B,C can do of the work in 1 day .
⇒
⇒ ⇒ = 1 , which means the whole work is completed .
∴ Together A,B,C can complete the work together in 1 day.