If 10 men (or) 18 boys can do a piece of work in 15 days, then 15 men and 13 boys together will do twice the work in
Answers
Answered by
1
10men = 18 boy..
men/boy = 18/10 = 9/5. ,so men=9 boy=5
-now total work = 10(men)*18= 10*(9)*18= 1620
- so (15m+13b)*x = 1620
(15*9 + 13*5)*x = 1620
(135+65)*x =1620
x=1620/200
x= 81 ans