if 12 men complete a piece of work in 20 days in how many days would 15 men complete the same work
Answers
Answered by
1
Answer:
16 DAYS
Step-by-step explanation:
It would take 16 days. You can’t use proportions because 12 men finishing something in 20 days is not equal to 6 men finishing in 10 days. How you would calculate this is by doing 12 men times 20 days. You’re answer is 240.
For the 15 men, take 240/15 and you will get 16. To prove this correctly let’s say there are 240 parts of the project and each guy can do 1 per day. 12 men would take 20 days and 15 men would take 16 days.
Answered by
147
Answer:
16 days
Step By Step Explanation:
Let the required number of working days be x.
Here, the number of men and their working days are in inverse proportion.
∴ 12 : 15 = x : 20
⇒ 12 / 15 = x / 15
⇒ 15x = 12 × 20
⇒ x = 240 / 15
⇒ x = 16 days
Hence, the required number of working days is 16 days.