if 15 men do a piece of work in 7 days in how many days can 21 men do the work
Answers
Answered by
6
Answer:
Step-by-step explanation:
Attachments:
Answered by
1
5 days is your answer let me clear
15×7=105÷21=5
15×7=105÷21=5