if 18 people can finish a piece of work in 8 days how many people will be needed to finish it in 3 days
Answers
Answered by
2
8 days = 18 people
1 day = 18 ÷ 8
3 days = 18 ÷ 8 × 3
= 6.75
= 7 people
Hope it helps you!!!!!!
Please mark me as brainlliest!!!!!!!
Answered by
4
Step-by-step explanation:
1 man takes ( 18 x 8 ) = 144 days to complete the same piece of work.
144 ÷ 3 = 48
so 48 people will be needed.