if 35 men can do a work in 8 days .how many men could do the same work in 10 days.
Answers
Answered by
3
In 8 days, number of men required = 35
In 10 days, number of men required = (35/10)×8
= 3.5×8 = 28 men
In 10 days, number of men required = (35/10)×8
= 3.5×8 = 28 men
2007shoaibpb0hbc:
8days = 35men
Answered by
0
35.8=1
35=1/8
35.8/10=x
28=x
28 men
35=1/8
35.8/10=x
28=x
28 men