If 4/7 of a piece of work is completed in 7/4 days, in how many days can rest of the work be completed ?(a) 7/3 days(b)3/7 days(c) 21/16 days(d) 16/21 days
Answers
Given :-
- (4/7) of work completed in = 7/4 days.
To Find :-
- in how many days can rest of the work be completed ?
Solution :-
we know That, Total work is 1.
→ work done = (4/7) of work.
→ work Left to be done = 1 - (4/7) = (7-4)/7 = (3/7) Piece of work.
Therefore,
→ (4/7) of work completed in = 7/4 days.
→ 1 unit of work completed in = (7/4) /(7/4) = (7/4) * (7/4) = (49/16) Days.
→ (3/7) of work completed in = (49/16) * (3/7) = (7*3)/16 = (21/16) Days. (Option C) (Ans.)
Hence, rest of the work be completed in (21/16) Days.
________________________________
- 4/7 of a piece of work is completed in 7/4 days
________________________________
- in how many days can rest of the work be completed ?
________________________________
Let the whole work be 1
Than,
↪ Remaining work = {1-(4/7)}
↪Remaining work = {(7-4)/7}
↪Remaining work = (3/7)
↪(4/7) unit of work is done in = 7/4 days
↪1 unit of work completed in = 7/4 × 7/4
↪1 unit of work completed in = (49/16) or 3.0625 Days
↪(3/7) units of work completed in = (49/16 × 3/7)
↪(3/7) units of work completed in = (7×3)/16
↪(3/7) units of work completed in = (21/16) or 1.3125 Days or Option (C)