if 4 men or 6 woman can do a piece of work in 24 days , then the no .of men should accompany 3 women to complete the work in 16 days​

Answers

Answered by vikashdas10581
1

Answer:

Thanks for free points

Answered by nilumarmat09
4

Step-by-step explanation:

If 4 men or 6 women can do a piece of work in 24 days, then how many men should accompany 3 women to complete the work in 16 days?

Free French class demo. Offer ends tonight!

The work requires 4*24 or 96 man-days or 6*24 = 144 woman-days.

In other words 1 man is equivalent of 1.5 women.

If 3 women are available for 16 days they would do 3*16 = 48 woman-days of work. The balance of 144–48 = 96 woman-days has to be done by the men.

96 woman-days = 64 man-days. Now these 64 man-days of work is to be completed in 16 days or 4 men are adequate.

So 3 women and 4 men can completed the work in 16 days.